The structure of both buildings has progressed rapidly over the last few months, resulting in the project being ahead of programme.
Our site team, form worker, steel fixer and concreting subcontractors have developed an efficient sequence of works resulting in slab cycles of 4 – 5 days which will continue until we top out.
Infinity are looking forward to the structural steel on Building A commencing very soon.
There is nothing better that seeing a well-run, safe, coordinated and efficient site motoring along with great co-operation at all levels.
Meet the team:
Client: Scape
Architect: AJ+C
Engineer: Meinhardt Group